Status MicroLab, July 2, 2008.
Status office tower, July 2, 2008.
Landscaping, NW corner, July 2, 2008.
Cleaning up the surroundings, June, 2008.
Completing the West facade, June 4-6, 2008.
Disassembling the man-lift, May 28, 2008.
Progress on the NW corner of the MicroLab, June, 2008.
Building status, May 27, 2008.
Painting the MicroLab, May 7-12, 2008.
MicroLab roof, May 1-9, 2008.
Building status, April 10, 2008.
Bye-bye crane, March 28, 2008.
Airhandler installation, March 5 & 12, 2008.
Building status, March 5, 2008.
South Terrace -- February 26,27, 2008.
Micro_Lab Progress -- February 22-26, 2008.
Micro_Lab Wall -- January 29, 2008.
Pour of the Micro-Lab roof -- January 28, 2008.
Status of the Micro-Lab -- January 28, 2008.
Status Office Tower -- January 28, 2008.
Building Status -- December 21, 2007.
MicroLab Walls -- December 19, 2007.
Roof Work -- December 11-13, 2007.
Building Tour -- December 7, 2007.

PICTURES OF PHASE 2b: CONSTRUCTION THRU COMPLETE SHELL


PICTURES OF PHASE 2a: CONSTRUCTION THRU TOP-OUT OF STEEL FRAME


PICTURES OF PHASE 1: DEMOLITION OF DAVIS HALL AND EXCAVATION


Link to the CITRIS PROJECT PAGE



Login to Ken Goldberg's live WebCam looking at the CITRIS site from the 4th floor of Cory Hall

Page Editor: Carlo H. Séquin