|
Topping-out ceremony -- March 2, 2007. |
|
Topping out the steel structure -- March 2, 2007. |
|
Preparation for the topping-out ceremony -- March 1&2, 2007. |
|
More braces -- Feb. 21, 2007. |
|
Welding -- Feb. 18, 2007. |
|
NanoLab floor -- Feb.17, 2007. |
|
The growing passenger elevator -- February, 2007. |
|
Columns -- Feb. 15, 2007. |
|
Beams -- Feb. 15, 2007. |
|
A sculpture garden ?? -- Feb. 14, 2007. |
|
More steel ! -- Feb. 13, 2007. |
|
Steel ! -- Feb. 12, 2007. |
|
Nanolab deck -- Feb. 12, 2007. |
|
Wall construction -- Jan. 29 - Feb. 12, 2007. |
|
Columns, beams, and braces -- Feb. 6, 2007. |
|
Steel work -- Feb. 2, 2007. |
|
More steel -- Jan. 31, 2007. |
|
Steel -- Jan. 30, 2007. |
|
Allen Barker at the top -- January 19, 2007. |
|
Steel deck at the floor F3 -- January 19, 2007. |
|
The first level of steel decking -- January 17, 2007. |
|
The steel frame starts to rise -- January 16, 2007. |
|
Steel arrives in huge quantities ! -- January 15, 2007. |
|
Ongoing wall constructions -- January 10-19, 2007. |
|
Wall and Pillar Constructions -- January 5-8, 2007. |
|
Wall Construction -- December 13-20, 2006. |
|
The Big Pour of the Slab of Floor 1 -- December 13, 2006.
TIME LAPSE MOVIE -- (This takes a minute to load!)
|
|
Construction Activities -- December 6, 2006. |
|
Construction Activities -- 11/29 - 11/30, 2006. |
|
Wall Construction -- 11/15, 2006. |
|
Lots of Gravel -- 11/14, 2006. |
|
Construction Activities -- 11/05 - 11/09, 2006. |
|
653 cubic yards of concrete -- October 19, 2006. |
|
Re-bar and concrete -- October 2-6, 2006. |
|
Steel and re-bar -- September 25-30, 2006. |
|
More re-bar, more concrete ... -- September 12-21, 2006. |
|
View from the top ! -- September 15, 2006. |
|
More concrete for the wall of the MicroLab -- September 7, 2006. |
|
Crane Watching -- September, 2006. |
|
Placing a camera on the 5th floor of Cory Hall -- Aug. 25, 2006. |
|
Diverse construction activity -- Aug. 23, 2006. |
|
Big concrete pour for the future MicroLab -- Aug. 22, 2006. |
|
More digging for the foundations of the office tower -- August, 2006. |
|
Crane completed -- Aug. 21, 2006. |
|
The first half of the crane -- but where is the rest ?? -- Aug. 12, 2006. |
|
Getting ready for pouring foundations and installing the tower crane -- Mid July 2006. |
|
Contract has been awarded, the building site is ready for action -- July 2006. |